Sangamam 1

SANGAMAM PROGRESS

SPRINT 1

SWAT ANALYSIS – COMPLETED

LEGAL DUE DILIGENCE – COMPLETED

SOIL TESTING

ARCHITECTURAL DRAWINGS – COMPLETED

ACQUISITION OF LAND APPROVAL – COMPLETED 

PERCENTAGE OF COMPLETION – 5
SPRINT 2

ACQUISITION OF STRUCTURAL STABILITY REPORT – COMPLETED

ACQUISITION OF BUILDING PERMIT – COMPLETED

SITE MARKING

BORE WELL – COMPLETED

ACQUISITION OF FOUNDATION ARCHITECTURAL & STRUCTURAL DRAWINGS – COMPLETED

POOJA 

PERCENTAGE OF COMPLETION – 15
SPRINT 3

PILLING FOR FOUNDATON

CONCRETING FOR FOUNDATION

ACQUISITION OF BASEMENT ARCHITECTURAL & STRUCTURAL DRAWINGS – COMPLETED

ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS – COMPLETED

PILE CAP FABRICATION & SHUTTERING

PILE CAP CONCRETING 

INSTALATION OF UG SUMP

ESCAVATION 

PLINTH BEAM

BLOCK WORK 

TIE BEAM

EARTH FILLING 

FLOOR CONCRETING 

PERCENTAGE OF COMPLETION – 45
SPRINT 4

STEEL FABRICATION COLUMNS – COMPLETED

COLUMN MARKING FOR CONCRETING – COMPLETED 

COLUMN CONCRETING – TBC

ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS – COMPLETED

STAIRCASE MARKING – COMPLETED 

FABRICATION FOR BEAM – TBC

SHUTERING FOR ROOF SLAB – TBC

FABRICATION FOR ROOF SLAB 1 – TBC

CONCRETING FOR ROOF SLAB

PERCENTAGE OF COMPLETION – 50
SPRINT 5

STEEL FABRICATION COLUMNS – TBC

COLUMN MARKING FOR CONCRETING – TBC

COLUMN CONCRETING – TBC

ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS – COMPLETED

STAIRCASE MARKING – TBC

FABRICATION FOR BEAM – TBC

SHUTERING FOR ROOF SLAB – TBC

FABRICATION FOR ROOF SLAB 2 – TBC.

PERCENTAGE OF COMPLETION – 60
SPRINT 6

STEEL FABRICATION COLUMNS – TBC

COLUMN MARKING FOR CONCRETING – TBC

COLUMN CONCRETING – TBC

ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS – COMPLETED

STAIRCASE MARKING – TBC

FABRICATION FOR BEAM – TBC

SHUTERING FOR ROOF SLAB – TBC

FABRICATION FOR ROOF SLAB 3 – TBC

PERCENTAGE OF COMPLETION – 70
SPRINT 7

STEEL FABRICATION COLUMNS – TBC

COLUMN MARKING FOR CONCRETING – TBC

COLUMN CONCRETING – TBC

ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS – COMPLETED

STAIRCASE MARKING – TBC

FABRICATION FOR BEAM – TBC

SHUTERING FOR ROOF SLAB – TBC

FABRICATION FOR ROOF SLAB 4 – TBC

PERCENTAGE OF COMPLETION – 80

FINAL SPRINT

BLOCK WORK FOR FLOOR 1 INCLUDIG SIL & LINTEL BEAM – TBC

INSTALATION OF LIFT – TBC

ELECTRICAL PIPING & CONDUIT – TBC

PLUMBING PIPING & CONDUIT  – TBC

ELECTRICAL CHASING – TBC

ELECTRICAL FITINGS -TBC

PLUMBIG FITTINGS – TBC

INSTALATION OF UPVC WINDOWS – TBC

INSTALATION OF DOORS  TBC

SANDING, PUTTY & PRIMER – TBC

COLURING EMULSION PAINT – TBC

INSTALATION OF WTP – TBC

INSTALATION OF SOLAR PANEL – TBC

INSTALATION OF COMON AREA LIGHTS, ELEVATION FOCUS LIGHTS – TBC

LANDSCAPING – TBC

PERCENTAGE OF COMPLETION – 95

SNAG WORK

FULL ELECTRICAL QC – TBC

FULL PLUMBING QC – TBC

ALL FLORING QC – TBC

ALL JOINERIES QC – TBC

ALL DODO WALLS QC – TBC

ALL CHECK WALLS, DRINAGE PITS, SEPTIC, SUMP, LANDSCAPE, ELECTIRCAL FITTINGS QC – TBC 

PERCENTAGE OF COMPLETION – 100

HANDOVER 

ARCHITECT, SE, MEP CONSULTALT, CMDA INSPECTION – TBC

ALL CLIENT ACCEPTNCE INSPECTION – TBC

ISSUANCE OF ALOTMENT LETTER (CAR PARKING) – TBC

ISSUANCE OF POSSESION LETTER – TBC

HANDOVER CERMONY – TBC

EXPECTED POSSESION DATE - 25/04/2024